Launch of the production after reconstruction at Cheboksarsky city milk plant LLC
About the project
Since 2017 the enterprise has been implementing the project of modernization, reconstruction and construction of the plant with an investment of more than 1.2 billion rubles by 2021. With the completion of the project, the processing of unpasteurized milk in the republic will increase by 30% and reach 300 thousand tons per year, as a result, the export of unpasteurized milk outside the republic will decrease, and the sales geography of dairy products produced in the republic will grow, it is also planned to supply the products in Kazakhstan and other countries near abroad countries.
Main characteristics
Investment amount | 1200 Mio rubles |